If I'm just boosting up the time a bit, can I turn in the critical path sheet (the table) with it, rather than the entire project summary?
Also, if each flat takes 2 hours, but our work day is 3:50... how do we do that since we can't just build both flats in 1 day... Is it something like:
Day 1:
Build A
Build B
Day 2:
Finish B... ?
If you are changing your estimate, I would like to have a new estimate. You should likely include it with your critical path as well.
You need to place your estimated hours over the available lin time. If that means something splits into two calls, then that’s the way it goes. Also, think about the validity of that 3:50 assessment (I am not saying it is wrong - just to consider).