Wednesday, April 25, 2012

Monday, February 14, 2011

Basic PTM - Critical Path

A student asks:
I was wondering if every group's machine has to end in pressing a button or if only the last group?
and then I say:
There doesn’t have to actually be a button for each group, but the final action for each group should be a motion that could press a button. Consequently the first action of each group should be something that is initiated by a motion that could be pushing a button.

Wednesday, February 02, 2011

Basic PTM - Estimating

A student asks:
Hi David,

[my partner] and I were wondering if there is a specific number we should use as our budget for building the rocket flat. The sheet doesn't list one, and we need it to calculate our consumable allowance for each unit element sheet.

Also, the sheet gives a technical drawing and an artistic one. The artistic drawing includes additional lighting elements; should those be included in our estimates?

David says:

You don't need to know the overall budget to apply a consumables allowance.

I had meant to give you an available budget though. Let's do this:

$500 Materials

2 "crew", 2 days, 10 hours per day
1 "helper", 1 day, 4 hours
Build from the tech drawing.

Tuesday, January 11, 2011

Basic PTM - Organizational Charts

One student says:

I've been talking to some people in the class, and a few of them have said that the first part of the Theater Hierarchy Organizational Chart is supposed to be fancy and creative, but as far as I understand you basically wanted a clean looking version of what you wrote on the board.

David says:

Yes. Part one should just be a b-flat, normal depiction of the "prototypical regional" production department. You can spruce it up if you want I suppose, but the content and relationships should just be what was discussed and what was on the board.

Wednesday, March 18, 2009

Basic PTM - Assorted

David,

Do we still need to make comments this week for the News Week Quiz? I realize we do not have class this week, but are the comments still needed?
No quiz this week. Comments from last week and this week will roll over into next week.
David-

Are we expected to create a 3D "arts and crafts" type object for the second chart, or can we use different line styles to distinguish between hire/fire and "can't do my job without"?
You should do whatever you think you need to do to properly represent the process. If you can do it on paper that's fine, if you need more dimensions that's fine too.
Hi,

I just wanted to clarify due dates for our next two assignments. Are both the organizational charts and the new assignment we got today on forms due on April 2? They both have the same date, so I was just checking that they are in fact both due that day.
People, this is the kind of crap that happens when you don't do a schedule. Lets extend the paperwork deadline to April 9.

Monday, March 02, 2009

Basic PTM - Calendar & Critical Path

For the Critical Path/Calendar assignments, you say assume (2) people, but we may have a third if necessary. Lets say we had budgeted for (4) on the Elements sheet. Should we alter the Elements sheet to reflect a maximum of (3) people, or just make that change on the Critical Path/Calendar and have the documents be out of sync? Basically, if we need to make a change, should we track changes backwards or not.
You can, should you so choose to rejigger your original estimate to reflect no more than the 2(sometimes+1) people available for the calendar assignment in order to force consistent lin times. If you do so, you do not have to update the earlier assignment.

Or you can do nothing and have the assignments not match, they are being evaluated individually.

Friday, February 27, 2009

Basic PTM - Critical Path Assignment

I have a critical path question for you. On my estimating sheet, I combined the "cutacetate" and "install acetate" into one action because both took so little time. Should I count both these actions as one on my critical path?
Either way.

Thursday, February 26, 2009

Basic PTM - Critical Path Assignment

I have a question regarding the critical path analysis and the scheduling. On the critical path analysis, do we need to differentiate which department is doing the work (since there are a few hand-offs) or should all of the tasks be put into a single pool and the predecessors be determined blind of what department is doing it? Or is this irrelevant because the entire crew is ourselves and a buddy?
What do you need to do critical path? Label, Time to complete, Immediate Predecessor.
For the critical path assignment, should we assume we only have two people or is that only for the calendar?
What do you need to do critical path? Label, Time to complete, Immediate Predecessor.

Monday, February 23, 2009

Basic PTM - Estimating

So we are confused about the support for the flat. two people think you said we need to account for building bracing (a-frame/jack), while two think you said to not account for any support. help?
there will be something for it to lean against, you do NOT have to bid it in

Thursday, February 19, 2009

Basic PTM - Estimating Assignment

Do you want our element sheets etc. made in excel or will a simple table work?
Also, are we assuming that everything is being bought?
There is no requirement to use Excel.
You do not have a stock of material to draw from.

Wednesday, February 06, 2008

Basic PTM - Estimating Project

DoinMyEstimate (11:41:25 PM): is ripping 1x6 in half an acceptable solution for the rocket flat?
eProf (11:41:40 PM): Hi
DoinMyEstimate (11:42:32 PM): hello
eProf (11:42:40 PM): who is this?
DoinMyEstimate (11:43:00 PM): DoinMyEstimate
eProf (11:43:06 PM): cool
eProf (11:43:17 PM): 1x3 would be standard for this type of construction
eProf (11:43:31 PM): getting that by buying 1x6 and ripping it down would also be standard
DoinMyEstimate (11:43:37 PM): ok
DoinMyEstimate (11:43:39 PM): thanks
eProf (11:43:45 PM): np

Tuesday, February 05, 2008

Basic PTM - Estimating Assignment

Question:
Hi Dave,
A couple of us from Basic PTM class were confused about some of the elements of assignment one. Is the project summary sheet and description done by each group collectively? Or do we do those elements separately? Any info would be much appreciated!

Answer:
Each pair can turn in one set of paperwork with both names.

db

Monday, January 28, 2008

Basic PTM - Estimating Assignment

Some people have been asking for this:

Monday, April 30, 2007

BasicPTM - Meeting Package

Workin4TheMan (6:31:44 PM): Hey, TheMan
TheMan (7:31:46 PM): yuh
Workin4TheMan (6:32:04 PM): Quick question about the revised schedule for the meeting paperwork
TheMan (7:32:00 PM): k
Workin4TheMan (6:32:24 PM): Is this revision as of the end of the meeting?
Workin4TheMan (6:32:33 PM): Or as of the due date?
TheMan (7:32:34 PM): changes that were made/became apparent at the meeting
TheMan (7:32:54 PM): if you have others
Workin4TheMan (6:33:05 PM): Because our Tuesday Foundations class was cancelled, but we were not informed until after the meeting
TheMan (7:33:00 PM): you can include them
TheMan (7:33:11 PM): but you need to indicate that they didn't come up at the meeting
TheMan (7:33:19 PM): lest people who are there might think they missed something
Workin4TheMan (6:33:47 PM): Is it clearer to create two revised schedules?
TheMan (7:34:00 PM): I don't think so
Workin4TheMan (6:34:31 PM): Just note that the commitment in question was changed after the meeting?
TheMan (7:34:36 PM): and put it in your wrap up memo that way too
Workin4TheMan (6:34:53 PM): Ok, thanks
TheMan (7:34:49 PM): np

Saturday, April 28, 2007

Basic PTM - Meeting Package

WrappingItUp (11:05:04 PM): i'm doing my meeting paperwork
WrappingItUp (11:05:26 PM): when you say the schedule of the commitments should be revised,
WrappingItUp (11:05:51 PM): do you mean we should update them
WrappingItUp (11:06:02 PM): or just add the wrap up memo
IHaveAHeadache (11:06:16 PM): what does it say?
WrappingItUp (11:06:51 PM): revised schedule of commitments to be distributed with the wrap up memo
WrappingItUp (11:07:01 PM): so is the schedule revised by itself
WrappingItUp (11:07:13 PM): or adding the wrap up memo automatically revise itself?
IHaveAHeadache (11:07:28 PM): I don't have it in front of me
WrappingItUp (11:07:38 PM): oh
IHaveAHeadache (11:07:39 PM): but I would assume that you did a schedule for the day of
IHaveAHeadache (11:07:53 PM): and then now you are doing a revised schedule based on what we talked about
WrappingItUp (11:08:24 PM): ok, so the schedule should be updated based on the lecture
WrappingItUp (11:08:26 PM): hm
WrappingItUp (11:08:35 PM): one more question
WrappingItUp (11:08:51 PM): is wrap up memo simply the note summary from the meeting?
WrappingItUp (11:09:08 PM): what's been discussed, what is concluded?
IHaveAHeadache (11:09:15 PM): The wrap up memo gives the details from the meeting
IHaveAHeadache (11:09:22 PM): who was there
IHaveAHeadache (11:09:25 PM): what was discussed
IHaveAHeadache (11:09:32 PM): any decisions that were made
IHaveAHeadache (11:09:41 PM): any assignments that were made
IHaveAHeadache (11:09:53 PM): anything that got put in the parking lot for alter discussion
WrappingItUp (11:09:58 PM): who is the reader of the wrap up memo?
IHaveAHeadache (11:10:11 PM): the people that were at the meeting
WrappingItUp (11:10:16 PM): ok
IHaveAHeadache (11:10:17 PM): and anyone that missed the meeting
WrappingItUp (11:10:33 PM): awesome
WrappingItUp (11:10:42 PM): do i get to be posted on the blog this time?
WrappingItUp (11:10:50 PM): with the cool nickname?
IHaveAHeadache (11:11:01 PM): I was thinking you would be "WrappingItUp"
WrappingItUp (11:11:11 PM): lol
IHaveAHeadache (11:11:15 PM): and I would be "IHaveAHeadache"

Tuesday, April 24, 2007

Basic PTM - Meeting Package

MakingAList (4:24:24 PM): hey CheckinItTwice, for our agenda, should we just put on their what you gave us (review for the test, discussing work we have left, and next year's production dept. preferences) or should we add something else? or elaborate on those?
CheckinItTwice (4:26:26 PM): your agenda should be what we're going to do
MakingAList (4:26:39 PM): ok... so its ok if it's really short?
CheckinItTwice (4:27:03 PM): if thats what we're doing
MakingAList (4:27:10 PM): ok, thank you
MakingAList (4:28:03 PM): do agenda's include times?
CheckinItTwice (4:28:16 PM): sometimes
CheckinItTwice (4:28:25 PM): how long something will take
CheckinItTwice (4:28:41 PM): if you poke around a little with templates you find all kinds of things
MakingAList (4:28:48 PM): ok, is it alright if it's not accurate?
MakingAList (4:28:50 PM): the time?
CheckinItTwice (4:29:06 PM): its only a best estimate
MakingAList (4:29:20 PM): ok. awesome
MakingAList (4:41:07 PM): for the schedule being distributed, were you thinking of classes left in addition to projects? or is that strictly homework based?
CheckinItTwice (4:43:05 PM): whatever you think best tells the story
MakingAList (4:43:11 PM): ok

Monday, April 16, 2007

Basic PTM - Organizational Chart

VascoDeOrgChart (9:10:18 PM): hey eProf
eProf (10:10:45 PM): hey what?
VascoDeOrgChart (9:11:20 PM): on our organizational chart, would we also add the flow of information in the opposite direction? like, the various departments informing the "higher-ups" what's going on and if they've executed certain directives?
eProf (10:12:07 PM): Anything to properly characterize the flow of ideas in the execution of a production
VascoDeOrgChart (9:12:35 PM): even if that flow of information is just to make sure things are getting done?
eProf (10:13:13 PM): a path of information flow is a path of information flow
VascoDeOrgChart (9:13:21 PM): ok, just checking. thank ya
eProf (10:14:17 PM): np

Basic PTM - Paperwork Project

LeftItTooLong (7:29:43 PM): hi NoRealHelp
NoRealHelp (8:29:53 PM): hi
LeftItTooLong (7:29:56 PM): does it have to be a real inventory for the school of drama?
LeftItTooLong (7:30:02 PM): or just a real inventory
LeftItTooLong (7:30:03 PM): ?
NoRealHelp (8:30:21 PM): sod
LeftItTooLong (7:31:10 PM): oh, thats a shame
LeftItTooLong (7:31:11 PM): thanks

Saturday, April 14, 2007

Basic PTM - Paperwork Project

FormOPhile (7:54:27 PM): hey NetProf, for the paperwork assignment, or for paperwork in general; if there is a form/document that is two pages, i know i need to # the pages but is it better to actually have them as two pages or should i do it as a double-sided document?
NetProf (7:55:01 PM): if it is double sided
NetProf (7:55:15 PM): then it is good make sure you include a summary on the front
NetProf (7:55:32 PM): the important part is to make sure that the information on the back isn't missed
NetProf (7:55:46 PM): you can also do an 11x17 form
NetProf (7:55:49 PM): on one side
FormOPhile (7:56:18 PM): would a "SEE REVERSE" in the bottom header work as a summary?
NetProf (7:56:52 PM): its a band-aid
NetProf (7:56:55 PM): not a solution
NetProf (7:57:09 PM): you also have to anticipate the thing being copied
NetProf (7:57:17 PM): and then all of a sudden it's 2 pages
FormOPhile (7:57:29 PM): okay
FormOPhile (7:58:26 PM): i think in the end it might just be easier to do two pages, ehh?
NetProf (7:58:34 PM): maybe
NetProf (7:58:48 PM): I personally like the 11x17 forms
NetProf (7:58:58 PM): they xerox down to 8.5x11
NetProf (7:59:08 PM): but 2 pages are ok
NetProf (7:59:16 PM): make sure its clear there are two pages
FormOPhile (7:59:43 PM): but as distribution the 11x17 forms don't get wonky?
NetProf (8:00:16 PM): they are also somewhat problematic
NetProf (8:00:29 PM): there really are no perfect choices here
FormOPhile (8:00:38 PM): gotcha
FormOPhile (8:01:32 PM): NetProf . . . i am not going to lie, i really like this paperwork stuff. i never thought i would
FormOPhile (8:01:35 PM): lol
FormOPhile (8:01:45 PM): thanks have a good night.

Basic PTM - Paperwork Project

BuddingBureaucrat (6:44:23 PM): hey, eProf
eProf (6:44:31 PM): hi
BuddingBureaucrat (6:44:43 PM): can we use cue sheets or scene breakdown for our paperworks?
eProf (6:44:57 PM): if they are a form or a template
eProf (6:45:05 PM): for use on several projetcs
BuddingBureaucrat (6:45:10 PM): oh
eProf (6:45:15 PM): not for a single occasion
BuddingBureaucrat (6:45:31 PM): as long as i can use it later, it's fine?
BuddingBureaucrat (6:45:34 PM): great!
BuddingBureaucrat (6:45:42 PM): thanks
eProf (6:45:47 PM): I wouldn't say "later"
eProf (6:46:02 PM): I would say "on multiple occasions"
BuddingBureaucrat (6:46:25 PM): oh! it should be multi purpose, huh
eProf (6:46:31 PM): so if it was a thing you could use only a couple of times - that's not so great
eProf (6:47:02 PM): but if it has a potential for use on bunches of projects then yes
eProf (6:47:11 PM): not "multi-purpose"
BuddingBureaucrat (6:47:18 PM): eh...?
eProf (6:47:19 PM): "multi-instance"
BuddingBureaucrat (6:47:28 PM): wouldn't they be kind of the same thing, tho?
eProf (6:48:33 PM): multi purpose means you can do different things with it
eProf (6:48:40 PM): what I mean is doing the same thing
eProf (6:48:43 PM): multiple times
BuddingBureaucrat (6:48:58 PM): ok..
BuddingBureaucrat (6:49:23 PM): they just have to be flexible enough so that i could use.... it, right..?
eProf (6:50:18 PM): ok
BuddingBureaucrat (6:50:43 PM): ok, thanks!